Contingency sensitivity calculator

Test how contingency, escalation and delay assumptions change your total scenario exposure. Calculations happen in your browser.

ZAR, excluding contingency

R

Your own assumption. This isn't a recommended or required rate.

%

Months

mo

Finance, holding, site costs per month

R

Months of delay to test

mo

% of base cost

%

Scenario exposure

R 28,950,000

R 3,950,000 above base cost over a 21-month programme

Calculation breakdown
Base costYour estimateR 25,000,000
Contingency reserveBase × 10%R 2,500,000
Escalation allowanceBase × 4%R 1,000,000
Delay carrying cost3 mo × R 150,000R 450,000
Total exposureR 28,950,000

Assumptions & disclaimer

This is an illustrative sensitivity model, not a cost estimate or professional advice. Contingency percentages are scenario inputs, not regulatory rules or recommendations. Escalation is applied as a single allowance on base cost. Confirm figures with your quantity surveyor.